Data centers are now the largest single driver of US electricity load growth. Grid Strategies projects 166 GW of peak load growth over the next five years, with roughly 55% attributed to data centers. The grid cannot connect that demand fast enough. Two paths are emerging: build around the grid with private generation, or build with it through flexibility and shared infrastructure. Which path wins will reshape the electricity system.
The scale
166 GW of projected peak load growth over five years, 55% from data centers. The 5-year build cycle for transmission and generation is too slow to absorb that pace, so developers are racing to provision their own supply while interconnection queues stretch 4-6 years.
What's happening
Developers are building around the grid: Cleanview counts 59 data centers with about 90 GW of capacity that plan to build their own behind-the-meter power, at varying stages of development (92% of them announced since the start of 2025). Separately, Cleanview reports about 2 GW of behind-the-meter generation operating. Grid-cooperative alternatives exist but remain orders of magnitude smaller in deployed capacity. The gap between flexibility narrative and flexibility deployment is the central tension.
What the evidence shows
AEP Ohio's data-center queue is one example: it reported ~30 GW earlier, and 36 sites totaling ~13 GW have since signed up for formal studies. Technical flexibility is demonstrated (EPRI: 25% power reduction, peer-reviewed). Modest curtailment could accommodate large load (Duke: a modeled 98 GW, with average curtailed energy equal to 0.5% of maximum annual consumption). But flexibility only activates when it is a condition of access, not a voluntary economic choice.
What should be piloted
Utility-administered VPPs near constrained substations (Xcel: 200 MW, co-funded by Google). BYOC programs linking DC interconnection to community flexibility (Voltus/Octopus). Tariff-based flexibility as an interconnection condition. These mechanisms exist. The question is whether they scale before political backlash ($64B blocked or delayed, 300+ state bills) forecloses the opportunity.
166 GW
Projected 5-year U.S. peak load growth
Up from 24 GW in the 2022 baseline to 166 GW in the 2025 Grid Strategies report, a sevenfold revision in three years.
Grid Strategies 2025 National Load Growth Report55%
Share of projected U.S. peak load growth linked to data centers
Roughly 90 GW of the 166 GW forecast.
Grid Strategies 2025 National Load Growth Report5-year peak load forecast, by Grid Strategies report vintage
Comparable 5-year peak-load-growth revision series as presented in the Grid Strategies 2025 National Load Growth Report. Each value is that vintage's comparable baseline, not a cumulative total. 2022 is the FERC Form 714 baseline cited retrospectively by Grid Strategies (the firm's first standalone report was the 2023 report). 2024 shows the comparable baseline; the 2024 report's adjusted headline estimate reached 128 GW after adding forecast updates beyond the FERC baseline, but the mini-chart keeps the vintage-comparable series so the revision trajectory reads apples-to-apples.
Company guidance gives the scale in dollars. Five companies (Alphabet, Amazon, Meta, Microsoft, and CoreWeave) guide to $735-764B of calendar-2026 capital expenditure. Adding Oracle's $55.7B actual for its fiscal year ended May 2026 gives a gross, mixed-period sum of about $790-820B. It is gross company spending, so leased capacity may be counted in more than one company's figure, on a provider's books and a customer's. Definitions differ. Amazon's figure is capital expenditures across Amazon. Meta and Microsoft include finance leases. The totals include servers and chips as well as facilities and other capital spending. For the second quarter of 2026, Alphabet says about 60 percent of its technical-infrastructure investment went to servers and 40 percent to data centers and networking equipment. For its quarter ended June 2026, Microsoft says roughly two thirds of its capital spending was short-lived assets, mainly CPUs and GPUs. Announced private programs, such as Stargate's announced intention to invest $500 billion over four years, are not part of this sum and are not annualized here.
Inside a facility, electrical and mechanical systems dominate the construction cost. Published splits put electrical systems at 54% and mechanical systems at 22% of construction cost for air-cooled facilities (Turner & Townsend). Dgtl Infra's split is 40-45% electrical and 15-20% HVAC. Those shares describe the cost of a single facility, and the two were measured on different bases (Dgtl Infra's includes land, Turner & Townsend's covers air-cooled construction only). The Census Bureau measured $49.7B of private U.S. data center construction put in place in 2025 (buildings and their installed electrical and mechanical systems, excluding racks, servers, and land). As an illustration, applying the two published shares (40 to 54 percent) to that total gives $19.9B to $26.9B of electrical spending. Neither cited source directly measures U.S. data center electrical spending, so this is a scale estimate.
The Edison Electric Institute (EEI) projects capital spending by U.S. investor-owned electric companies: a 2026 total across all functions and a 2025 split by function.
$790-820B
Capital spending by the six companies above, 2026. Global, mostly servers and chips.
$238.8B
Projected capital spending by U.S. investor-owned electric utilities, 2026. Generation, transmission, distribution, and gas.
$19.9B to $26.9B
Illustration for 2025: Census data center construction at two published electrical shares (40 to 54 percent). Neither cited source directly measures this spending.
$103.6B
Utility transmission ($37.6B) plus distribution ($66.0B) capital spending, 2025. EEI projection.
On total spending, the six companies' figure is 3.3 to 3.4 times the utilities' projection. The two totals cover different things. The company figure is global, mostly servers and chips, and mixes calendar-year guidance with one fiscal-year actual. The utility figure is U.S. utility plant of every kind.
On electrical work, the illustration above is 19 to 26 percent of utility transmission and distribution spending. That comparison is closer in scope than the totals, with U.S. construction set against U.S. grid construction in one year, but it inherits the uncertainty of the two electrical shares. EEI compiles its functional split during the year and does not revise it to actuals. The split covers investor-owned utilities only. It includes the lines and substations built to serve data centers, which fall outside the Census data center category. Facility electrical and mechanical work and utility grid work draw on the same supply chain: transformers, switchgear, cooling equipment, and skilled electrical trades. Data-center demand is arriving into the same equipment and labor bottlenecks the grid already faces.
The reliability consequence is already visible beyond the U.S. forecast data: NERC says more than half of North American assessment areas (13 of 23) face elevated or high resource-adequacy risk over the next decade as load growth outruns planned generation and transmission buildout.
Split each market's net peak growth over 2026-2031 into its drivers. Large load is about 95% of ERCOT's forecast peak growth (46.8 of 49.3 GW). MISO's data-center growth is about three quarters the size of its peak growth (21 against 28 GW). PJM's forecast adjustments for new large loads (35.1 GW) exceed its net peak growth (34.6 GW), and we estimate nearly all of that is data centers. Across the three, large load equals 88 to 95 percent of forecast peak growth by our estimate. Total net growth across the seven ISOs is about 125 GW. Large load is 82 to 88 percent of it and data centers 61 to 67 percent, by our estimate. In CAISO and ISO-NE the growth is led by electrification, with large load a minor slice. Almost everywhere, energy efficiency and behind-the-meter solar pull the net back down.
Our estimates divide large-load additions by net peak growth, summed across the operators named.
Each bar splits one ISO's net summer-peak growth (2026-2031) into its drivers. Drivers that raise the peak extend right of zero. Drivers that lower it extend left. The tick marks net growth. Data centers are shown separately for CAISO and MISO. ERCOT's large load is split by type (data centers, crypto, and one combined segment for hydrogen, industrial, and oil and gas). ERCOT's hourly forecast adds 2.1 GW more large load than its chart shows by type. PJM's segment is its forecast adjustments for new large loads (+35.1 GW). They exceed its net peak growth (+34.6 GW), so the rest of its load declines slightly. PJM names two other items in those adjustments: port electrification in Public Service (about 0.07 GW by 2031) and a voltage-optimization reduction in Dominion (about 0.3 GW by 2031). NYISO and ISO-NE show large load as one segment. ISO-NE's electrification grows faster in winter, so its 0.7 GW summer figure understates it. Energy efficiency appears only where the ISO forecast itemizes it. MISO's figures are read from its 2026 forecast charts (its low case is +18 GW and its high case +39 GW). MISO breaks out its other drivers only over 2026-2046, so the remaining 7.5 GW is one segment. ERCOT's bar totals 49.9 GW from its annual summary. Its 95% share uses the 49.3 GW in its hourly forecast. ERCOT's 0.6 GW in Other closes the gap between its published summer peaks and its hourly forecast. Organic baseline is what remains after the itemized drivers. SPP's whole 6.1 GW sits there because its forecast itemizes nothing. SPP models its surveyed large loads (~11 GW) in a separate scenario, so they are left out here. Hover for each driver, peak basis, and source.
Regional detail
Data center location depends on workload type. Inference facilities (serving real-time user requests) cluster near fiber connectivity hubs and population centers for low latency. Training campuses (building AI models) can locate more remotely, prioritizing cheap power and land over proximity to users. Crypto mining follows the lowest-cost electricity regardless of location. Northern Virginia, Dallas-Fort Worth, and the Portland-Hillsboro corridor are the densest markets. Where these clusters overlap with congested transmission or retiring generation, grid pressure is highest.
Internet exchanges (blue) are facilities where multiple networks interconnect, providing the fiber backbone connectivity that data centers require. Their locations indicate where high-bandwidth fiber infrastructure already exists, a key factor in data center site selection alongside power availability.
Interconnection queues stretch 4-6 years, driven by a cascade of bottlenecks. The largest single delay is the study queue itself: ISOs cannot process the volume of requests. As of the end of 2025, PJM alone had about 1,100 active generator-interconnection requests totaling ~144 GW (LBNL, Queued Up 2026). When projects ahead in the queue withdraw (roughly 80% do), studies for remaining projects must be redone. Behind the study backlog, transmission infrastructure takes 5-10 years to build and permit. And equipment procurement, particularly power transformers, adds further delay.
128 weeks
Lead time for power transformers (up from a few months pre-2020)
30% gap
Supply shortfall for power transformers in 2025
+274%
Generator step-up transformer demand increase since 2019
Three categories of demand compete for the same manufacturing capacity: replacing aging infrastructure (~30-40% of demand, with over half of US distribution transformers beyond expected service life), connecting renewable generation (~30-35%, with ~2 TW in interconnection queues), and serving new large loads like data centers (~20-25%, the fastest-growing segment). The US has one domestic producer of the specialized electrical steel (GOES) used in transformer cores, and imports the majority of its power transformers.
Developers facing 4-6 year interconnection queues are responding in two ways. The choice between them is reshaping how the grid evolves.
Build around the grid
Construct behind-the-meter gas generation that bypasses the interconnection process entirely. Dominant by volume: Cleanview counts 59 data centers with about 90 GW of capacity planning their own behind-the-meter power, at varying stages of development.
Build with the grid
Trade flexibility commitments for faster access. Being tested in specific markets as five converging forces create conditions where the flexible path becomes viable.
The gas generation being built behind the meter at data center sites exceeds the total utility-scale gas additions planned for the entire US through 2028.
Capacity of data centers planning behind-the-meter power (Cleanview, mid-2026)
90 GW
59 projects. Cleanview behind-the-meter report page, read October 2026. Separately, Cleanview reports the status of the roughly 90 GW of generation capacity it identified across those projects: about 2 GW operating (2.2%), 1.2% under construction, 36% permitted, and 60% announced or early-stage.
Generation equipment Cleanview could identify in its February 2026 report (46 projects), by type
Equipment values are the data labels on the chart in the public Cleanview newsletter. They cover the generation deals Cleanview could identify and verify through permits, SEC filings, and press releases. The 90 GW and the equipment total are different measures from different Cleanview reports. One is the capacity of the 59 data centers in the mid-2026 report page. The other is the 30.9 GW of generation Cleanview could identify in February 2026, across 46 projects. Neither source says what generation will serve the rest of the data center capacity. Grid Strategies' separate figure of about 90 GW of data-center-linked peak growth, cited elsewhere on this page, is a different measure from a different source.
Why this matters for grid planning: Behind-the-meter generation is largely invisible to ISO operators. A data center with 500 MW of on-site gas may appear as zero load to the grid (fully self-served) or as 500 MW of sudden demand if the on-site generation trips. This creates phantom reliability risk that existing planning models do not account for.
Case in point: Virginia, July 2024
A single transmission fault near Fairfax, Virginia triggered six voltage dips over 82 seconds. Approximately 1,500 MW of data center load disconnected from PJM's grid simultaneously across 60 connection points and 25 substations as customer-side UPS systems switched to backup power. Grid frequency spiked to 60.047 Hz, exceeding NERC's target band. NERC's formal review noted: "The electric grid has not historically experienced simultaneous load losses of this magnitude in response to a fault." The operator had no visibility into when 1,500 MW would vanish or return. The BTM generation risk is the inverse: when on-site generators trip, hundreds of MW of load could appear on the grid with no warning. Both failure modes stem from the same root cause: operator invisibility.
Why this matters for clean energy: Most hyperscalers claim 100% renewable electricity via annual renewable energy credit matching. Behind-the-meter gas generation sits outside the utility's obligation. Virginia's Clean Economy Act mandates 100% carbon-free electricity from Dominion by 2045, but BTM gas at data centers in Virginia effectively circumvents this mandate.
Why it's happening: Speed to power. GPU-dense AI facilities generate an estimated $10-12 million per MW annually in compute revenue (general-purpose colocation is significantly lower). A 4-6 year interconnection queue represents tens of billions in lost revenue. Temporary or modular on-site gas (turbine-on-trailer units, pipeline-connected modular generation) can come online in months; permanent large-scale gas plants take longer but still typically beat utility interconnection timelines. Cleanview reports that 92% of these projects, about 82 GW, were announced since the start of 2025.
Selected behind-the-meter projects
| Project | Location | Capacity | Type |
|---|---|---|---|
| OpenAI Stargate | Abilene, TX | 7 GW total (361 MW initial) | 10 natural gas turbines + on-site battery storage + dedicated solar |
| VoltaGrid / Energy Transfer | Multiple (Oracle DCs) | 2.3 GW | Natural gas (pipeline-connected) |
| VoltaGrid / Vantage | Multiple | 1+ GW | Natural gas |
| Caterpillar campus | West Virginia | 2 GW | Natural gas turbines (Microsoft/NVIDIA) |
| Meta Louisiana | Louisiana | 2.26 GW | Natural gas (on-site power plant) |
| Joule | Utah | 1.3 GW | Fully islanded from Rocky Mountain Power grid (natural gas) |
| Meta Prometheus | Ohio | 200 MW | On-site natural gas generation |
Projects: Cleanview: Bypassing the Grid. Cleanview's mid-2026 report page tracks 59 data centers with about 90 GW of capacity, 92% announced since the start of 2025. Not all projects will reach completion.
Five forces are converging to make the brute-force path harder and the flexible path more attractive:
$64B in projects blocked or delayed. 78% of Americans concerned data centers will raise their energy bills.
300+ state bills filed in early 2026. AEP Ohio's cost-reflective tariff gave customers 45 days to request a formal load study and pay a fee. When that window closed in September 2025, 36 data-center sites totaling about 13 GW had signed up, against the roughly 30 GW AEP had previously described in its queue. Ohio manufacturers argue the remaining 13 GW is still overstated.
FERC's PJM co-location order (Dec 2025) and DOE's directive to accelerate large load interconnection are creating new mechanisms that reward flexibility.
One analysis suggests flexible data centers may reduce rates under specific conditions, but measured evidence currently shows DCs raising costs in concentrated markets (see next section).
Five-year peak load forecasts surged from 24 GW (Grid Strategies 2022) to 166 GW (Grid Strategies 2025), a sevenfold increase driven largely by DC demand. PJM is already revising forecasts downward based on stricter vetting. Forecast uncertainty favors flexible, incremental approaches over large upfront infrastructure.
None of these forces has stopped Path 1: Cleanview reports that about 82 GW of the roughly 90 GW in behind-the-meter projects was announced since the start of 2025. But they are creating conditions where the flexible path becomes viable for developers willing to trade some speed for lower political and regulatory risk.
Does data center flexibility actually work?
Data centers are technically capable of meaningful flexibility, but economically incentivized against it. Compute economics are roughly two orders of magnitude larger than flexibility value on a per-MW-year basis, so flexibility only activates at scale when it is a condition of interconnection, not a voluntary economic choice.
Frontier AI compute revenue is roughly 50–270x larger than modeled wholesale flexibility value.
DerivedGPU-dense AI capacity generates about $10–12M per MW-year in compute revenue, versus roughly $44K–$216K per MW-year from wholesale flexibility markets.
Wholesale value is normalized per MW-year of flexible load. Compute side: SemiAnalysis.
Proven at scale
As of September 2024, ERCOT had approved about 5.5 GW of large flexible load (facilities of 75 MW or more), and EIA's outlook assumed 9.5 GW approved by the end of 2025. The 9.5 GW is EIA's assumption of what ERCOT will have approved. Separately, ERCOT's independent market monitor measured about 4.6 GW of crypto-mining demand in 2025, more than 0.9 GW above its 2024 maximum. Approved capacity and measured demand are different measures, so these figures do not make a trend.
EIA's scenarios assume these facilities cut back when wholesale prices exceed $100/MWh. In 2025, controllable load resource capacity, which ERCOT dispatches directly, fell as mines moved to the Emergency Reserve Service, where they made up more than half of its capacity by year-end. The monitor's 2024 report adds that more than 2 GW of large flexible load capacity had been identified by spring 2023, and that the vast majority of such loads in ERCOT are cryptocurrency mines. Crypto mines can cut consumption quickly when prices rise. The monitor does not establish that the same flexibility is available from AI training or inference workloads.
ERCOT market monitor, 2025 State of the Market Report (May 2026): crypto-mining demandERCOT market monitor, 2024 State of the Market Report (June 2025), p. 27: large flexible load identified by spring 2023EIA Today in Energy (Oct 2024): ERCOT large flexible load approvals and EIA forecast assumptionDemonstrated
peer-reviewedEPRI DCFlex: 25% power reduction sustained 3 hours at an Oracle AI data center using 256 NVIDIA GPUs, with compute quality maintained.
Nature Energy (2025)Contracted
Google: 1 GW demand response integrated into utility contracts, targeting delay-tolerant AI training and batch processing workloads.
Google (2025)98 GW
of new load accommodated with a 0.5% average annual curtailment rate (~177 hours/year)
Duke Nicholas Institute found that modest curtailment could absorb the equivalent of most projected US data center growth without additional generation capacity. 0.5% is defined as an average annual load curtailment rate (partial curtailment events included), not a straight 0.5% of 8,760 hours. The report's corresponding hours figure is 177 hours/year.
Duke Nicholas Institute NI R 25-01: Rethinking Load Growth (2025)How flexibility trades for speed
Three models are emerging where developers trade flexibility commitments for faster grid access: deploying on-site storage that benefits both the data center and the grid, embedding demand response into power purchase agreements, or bringing their own accredited capacity to offset new utility infrastructure. This last approach is known as Bring-Your-Own-Capacity (BYOC): the data center developer directly procures generation capacity (clean energy contracts, batteries, or on-site resources) and makes it available to the wholesale market, rather than relying on the utility to build new infrastructure.
Aligned Data Centers + Calibrant Energy
Hillsboro, OR
First US deployment of a battery system purpose-built to accelerate data center interconnection. A 31 MW / 62 MWh battery charges when the grid has surplus capacity and discharges during peaks, converting the data center from a grid liability to a grid asset. This allowed Aligned to bring its 72 MW campus online faster than traditional interconnection would permit.
Aligned Data Centers (Oct 2025)Google 1 GW Demand Response
Multiple (I&M, TVA, Entergy, MN Power, DTE)
Google integrated 1 GW of demand response capacity into long-term utility contracts with five utilities. During grid stress events, an algorithm generates hour-by-hour instructions to limit non-urgent compute (such as video processing and ML training), rescheduling after the event. The commitment is embedded in the power purchase agreement, not a separate DR program.
Google (2025)Camus / encoord / Princeton ZERO Lab
One PJM utility territory (six candidate sites)
Bring-Your-Own-Capacity (BYOC) is a model where the data center directly procures accredited capacity (clean PPAs, VPPs, on-site batteries) and offers it into the wholesale market. Combined with a Flexible Grid Connection (accepting 20% conditional firm service, meaning the DC can be curtailed during system stress), this approach eliminates 273 MW of new generation build per GW. A 500 MW DC using this model reaches full operation in ~2 years, 3-5 years faster than traditional interconnection.
Camus / encoord / Princeton ZERO Lab (2025)The Camus/Princeton ZERO Lab analysis found that a 500 MW data center using flexible grid connection plus bring-your-own-capacity can reach full operation in approximately 2 years, 3-5 years faster than traditional interconnection. The combined model offsets nearly 100% of the traditional firm interconnection cost ($764M per GW).
Making other loads more flexible can also accelerate data center interconnection. Residential air conditioning (load factor 36%) creates the sharpest peak demand. Reducing residential peak through smart thermostats, managed EV charging, or demand response programs frees grid capacity that new loads can use. Brattle models up to $230 per EV per year in lower distribution grid costs than passive time-of-use charging ($135 versus unmanaged charging), with upgrades deferred by up to 10 years in its scenario (Brattle Group, January 2026).
What the economics look like
The measured evidence so far shows data centers raising costs for other ratepayers, not lowering them. In PJM's 2025/26 capacity auction, the RTO-wide clearing price rose 9.3-fold to $269.92/MW-day (from $28.92/MW-day the prior year). In that same auction the Dominion zone (Virginia/North Carolina, the densest US data center market) cleared at its zonal cap, $444.26/MW-day, $174.34 above the RTO-wide price and 64.6% higher. PJM attributed the zonal separation to insufficient resources inside those regions and transmission constraints limiting capacity imports. Areas with high DC concentration have seen electricity prices rise significantly. Harvard's Electricity Law Initiative has documented utilities entering below-cost-of-service contracts with data centers, with the difference recovered from other ratepayers.
One analysis suggests the economics can work differently under specific conditions. GridCARE (in partnership with Portland General Electric) modeled a scenario where a 1 GW flexible data center generates ~$142M in incremental annual earnings for a midsize utility, reducing rates by ~5% across all customer classes (~$103/year per residential customer). This model requires specific conditions: PGE has available capacity, Oregon's POWER Act created a regulatory framework, and PGE is small enough (~4 GW peak) that a single flexible DC is transformative. These conditions do not exist in the markets where DC demand is highest (PJM/Dominion, ERCOT, Georgia). The analysis is not peer-reviewed and has not been independently replicated.
An additional caveat: research by Knittel, Senga, and Wang (NBER) found that flexible data centers shifting load to off-peak hours can increase emissions when fossil generation dominates those hours. System cost benefits do not always equal emissions benefits; the outcome depends on the local generation mix and shift timing.
The gap between measured reality and the GridCARE scenario is the conditions: full cost-of-service rates, genuine flexibility commitments, and utility cooperation. Where those conditions exist (Oregon, parts of New England), the flexible path has an economic case. Where they do not (most of PJM, ERCOT, the Southeast), data centers are currently raising costs for other ratepayers.
For developers, the core question is not whether flexibility is conceptually valuable. It is which path gets power online fastest, through which counterparty, and with what tradeoff.
| Path | Status | Time to power | Counterparty | What the evidence says | Main tradeoff |
|---|---|---|---|---|---|
| BTM generation | Dominantmeasured | Months for temporary/modular; longer for permanent builds | Developer + equipment / fuel / infrastructure suppliers | About 90 GW of data center capacity across 59 projects at varying stages (Cleanview, mid-2026; 92% announced since the start of 2025). In February 2026 Cleanview could identify 22.8 GW of gas equipment, exceeding all utility-scale gas planned through 2028. Not all will be built. | Political risk rising ($64B blocked or delayed, 300+ state bills). Invisible to grid operators. Emissions liability. Circumvents state clean energy mandates. |
| Traditional interconnection | Standardmeasured | 4-6 years | Utility + ISO | Study queue backlog (PJM: ~144 GW active generation queue, ~80% withdrawal rate, end-2025 per LBNL Queued Up 2026). Transformer lead times (128 weeks) compound delay. 5-10 year transmission build cycle. | Slowest path. Queue position uncertain. Costs escalating as demand compounds. |
| Flexible interconnection / BYOC | Emergingmodeled + pilot | ~2 years (modeled) | Utility + capacity provider (Voltus, Calibrant, aggregator) | Camus/Princeton ZERO Lab: modeled 500 MW FGC+BYOC at six candidate sites within one PJM utility territory. Aligned: 31 MW battery deployed (Hillsboro). Voltus BYOC: product launched Sep 2025. | Accepts ~20% conditional firm service (curtailable during grid stress). Requires supportive regulatory framework. No large-scale operational proof yet. |
| Utility-administered VPP | Active pilotsapproved pilot | Case-specific | Utility | Xcel's Capacity*Connect (Phase 2, MN PUC E002/M-25-378): the Commission approved up to 200 MW; Xcel proposed an up-to-$430M budget. Google's Pine Island ESA petition (E002/M-26-170) commits $50M toward the program after load ramp; its MW allocation is not public. | Utility controls timeline and terms. Only available where utility has capacity and program willingness. Not broadly available. |
Cost-reflective tariffs (the AEP Ohio model) are not a direct path to power, but they change the economics developers face. In AEP Ohio's queue: ~30 GW reported earlier, and 36 sites totaling about 13 GW signed up for formal studies.
Not every market is at the same stage. Some have operational grid-cooperative mechanisms. Others are being forced toward them by political and regulatory pressure. The distinction matters: proven traction is a different signal than policy-forced transition.
Where Path 2 has real traction
Oregon (PGE)
active pilotMechanism
Utility-administered VPP + POWER Act large-load tariff
Best for
Hyperscaler siting, VPP operators, utility planners
Why now
PGE has available capacity (80+ MW now, 400+ MW by 2029). POWER Act framework in place. GridCARE partnership modeling rate impacts. Aligned/Calibrant battery deployed at Hillsboro.
Minnesota (Xcel / MISO)
active pilotMechanism
Utility-administered VPP (Capacity*Connect), 200 MW distributed batteries
Best for
Utility planners, investors (self-funding model), MISO watchers
Why now
MN PUC E002/M-25-378: approved up to 200 MW, Xcel proposed up to $430M. Google's ESA petition commits $50M. MISO wholesale revenues nearly self-fund deployment. Bypasses third-party aggregation opt-out.
ERCOT
proven for flexible loadsMechanism
Controllable Load Resource (CLR) + SB6 curtailment mandate + LFLF program
Best for
Large flexible loads, hyperscalers with curtailable workloads
Why now
Only ISO with operational DC controllable load resource (Lancium, 2020). 1-2 GW crypto curtailment proven. SB6 compels flexibility. Caveat: proven for stateless loads (crypto); transferability to AI workloads is limited.
Where the market is being forced toward Path 2
Ohio (AEP / PJM)
cost-reflective tariffMechanism
Cost-reflective tariff (85% minimum demand billing) + exit fees
Best for
Regulators, utility planners designing tariffs
Why now
AEP Ohio's queue: ~30 GW reported earlier, and 36 sites totaling about 13 GW have requested formal studies. Other PUCs could adopt the same model.
Northern Virginia (Dominion / PJM)
pressure zoneMechanism
GS-5 rate class (Jan 2027) + $11.8B transmission + 61 DC bills in 2026 session
Best for
Investors (political risk), regulators, hyperscalers with NoVA exposure
Why now
Highest regulatory pressure of any US market. $1.6B/year tax exemption at stake. GS-5 effective Jan 2027. Not a clean Path 2 market yet, but the most likely place where policy forces a transition from voluntary to mandatory flexibility.
Status reflects current evidence as of early 2026. "Active pilot" means an operational or approved mechanism with committed capital. "Proven policy lever" means demonstrated demand-side impact from regulatory action. "Pressure zone" means high political/regulatory pressure with mechanism design underway but not yet proven.
Utilities size transmission and distribution infrastructure for peak demand. Different customer classes contribute to that peak differently. Residential load is the peakiest (load factor ~36% in PJM, driven by air conditioning and heating). Commercial is moderately peaky (~46%). Data centers have one of the highest load factors of any customer class (~80%, nearly flat across all hours), comparable to continuous-process industries.
This creates a cost allocation tension. When high load factor customers like data centers grow, they increase total energy consumption without proportionally increasing peak demand. As baseload grows, the fixed costs of peak infrastructure spread across more kilowatt-hours, but the system is still sized for peak. Customers with lower load factors, particularly residential, can see rising costs even if their own consumption patterns have not changed, because the system is being expanded to serve growing baseload demand.
The mechanism is concrete. PJM bills capacity and transmission costs to each utility based on its load during a small handful of system-peak hours: five summer-afternoon peak hours for capacity (the customer-level number is called a Peak Load Contribution, or PLC), and the single highest hour of the year for transmission (a Network Service Peak Load, or NSPL). Whatever a customer pulls during those hours becomes their share of the bill for the next year. Other ISOs use related mechanisms: ERCOT allocates on 4CP (the four highest summer peaks), MISO and ISO-NE on a single annual peak, and CAISO on monthly peaks. The specifics differ, but in each case a few hours determine how infrastructure costs get allocated across customer classes.
For most residential customers in PJM, the allocator-hour load is not measured directly. Advanced metering infrastructure (AMI) reached about 87% of US meters by 2025, but parts of the Midwest and East Coast still lag, so the typical PJM utility computes a proxy PLC from the residential class's average summer load profile and scales it by each customer's annual kilowatt-hours. The 1.46x summer-peak ratio above gets baked into every residential customer's per-kWh capacity allocation regardless of their own behavior at peak. A family on vacation during the 5 PJM peak hours and a household running smart thermostats or scheduled EV charging both pay the same class-based PLC, even if their actual peak demand was below the class average. Data centers, by contrast, are interval-metered and get an individual PLC from their actual demand during those 5 hours: for a flat 1.0x load, that comes out roughly equal to the annual average.
New transmission and generation built specifically because of data-center load growth is recovered through this same allocation method, which spreads costs across all classes in proportion to their existing PLC share. The Union of Concerned Scientists counted $4.4 billion in 2024 PJM transmission upgrades attributable to data-center interconnections, socialized across customers in seven states (IL, MD, NJ, OH, PA, VA, WV). A Dominion witness testified at the Virginia SCC that of the $7.6 billion in planned new transmission infrastructure identified in Dominion's 2024 Integrated Resource Plan, residential customers will pay 55%, including for projects that serve only data centers. PJM's Independent Market Monitor attributed 40% of the December 2024 capacity auction's $16.4 billion in clearing costs (around $6.5 billion) to data-center load. Those costs flow to every customer in PJM via their utility's capacity rider, regardless of how flat or peaky the customer's own load is.
This is why every state with significant data-center load growth is now creating separate rate classes. Virginia's State Corporation Commission approved a new GS-5 rate class (general service for customers above 25 MW) in November 2025, requiring 85% minimum demand for transmission and distribution and 60% minimum for generation under 14-year contracts. Ohio's PUCO approved a parallel AEP Ohio tariff in July 2025: 85% minimum billing for up to 12 years for customers above 25 MW, with a three-year exit notice or a fee equal to three years of energy use. Oregon enacted the POWER Act in June 2025, requiring investor-owned utilities to create a separate large-load customer category. Pennsylvania's PUC issued a tentative model tariff for large-load customers in November 2025. PUCO Chair Jenifer French said the AEP Ohio order “safeguards non-data center customers on an industrial and residential level.” Virginia's SCC said the GS-5 class will “help insulate ratepayers from the costs around the rapid build-out and construction of infrastructure to support businesses such as data centers.” Both orders explicitly acknowledged the cost-shift risk the standard methodology was producing. The 78% of Americans concerned about data centers raising their energy bills are responding to a real and acknowledged risk, not a hypothetical.
Three policy approaches are being tested across states. Each has trade-offs, and none has been in place long enough to draw definitive conclusions about long-term outcomes.
Cost-reflective rate design
AEP Ohio's tariff (approved July 2025) requires data centers with peak demand over 25 MW to pay a minimum of 85% of contracted T&D demand and 60% of generation demand. Developers must demonstrate financial viability and pay exit fees if they withdraw. When the sign-up window closed in September 2025, 36 sites totaling about 13 GW had requested formal load studies, against the ~30 GW AEP had previously reported for the queue. By February 2026, AEP reported continued filtering to ~5.7 GW of demand under contract (AEP's own figure; critics question whether the original 30 GW was ever firm demand).
Trade-off: may deter smaller or early-stage developers who cannot meet the financial thresholds, potentially concentrating the market among the largest hyperscalers.
Flexibility mandates
Virginia HB 284 establishes a voluntary flexibility program for facilities over 25 MW by 2029. Maryland SB 596 explores incentives for peak shifting. These create behavioral incentives tied to grid conditions, not just financial commitments.
Trade-off: voluntary mandates have no penalties for non-participation. Effectiveness depends on implementation details still being developed.
Moratoriums
At least 12 states have filed data-center moratorium bills (1-5 year pauses). Virginia enacted none: its 2026 session passed 15 data center bills (cost-allocation, water, and siting measures; the ~$1.6B/year tax exemption is unresolved), and the lone state moratorium bill (HB 1515) was carried over to 2027. Virginia localities (Loudoun, Stafford, Fauquier, Prince William) have instead used zoning restrictions: removing by-right development, requiring special-use permits, or imposing setbacks, while grandfathering projects already in the pipeline.
Trade-off: moratoriums address immediate community concerns but do not change underlying incentives. They can push development to states with weaker protections rather than solving the problem. May be most appropriate as interim measures while permanent frameworks are developed.
Data centers are the grid's largest new load, its most politically contested infrastructure category, and technically capable of meaningful flexibility. The evidence shows they are not yet choosing flexibility voluntarily. What moves the needle is compulsion through rate design, interconnection conditions, and regulatory frameworks, not market incentives alone.
For developers and hyperscalers
Speed-to-power still favors BTM generation by deployed volume, but the political and regulatory cost of that path is rising. The clearest grid-cooperative alternatives now visible are flexible interconnection / BYOC models and utility-administered programs in territories with available capacity. The tradeoff is no longer just cost. It is accepting some combination of curtailment, tariff discipline, or utility control in exchange for earlier access.
For utility planners
AEP Ohio's rate design is one example: its queue shows ~30 GW reported earlier and 36 sites totaling about 13 GW signed up for studies. Transformer procurement now drives interconnection timelines more than regulatory process. Utility-administered VPPs (Xcel's up-to-200 MW Capacity*Connect) can create grid headroom without waiting for FERC 2222.
For VPP operators and aggregators
DC interconnection bottlenecks create local flexibility demand. Reducing peak near constrained substations frees capacity that accelerates large-load connections. Voltus's BYOC product (with Octopus residential resources) links DC interconnection directly to community flexibility investment.
For investors
Political risk is material: $64B blocked or delayed, 300+ state bills, moratorium bills in 12+ states. The measured evidence shows DCs raising rates in concentrated markets (PJM's Dominion zone cleared 64.6% above the rest of the RTO). Flexibility commitments de-risk projects by addressing the #1 community concern (78% worried about bills).
For regulators
Cost-reflective tariffs change the economics developers face. Moratoriums address symptoms but push demand to states with weaker protections. Flexibility as an interconnection condition (not voluntary), rather than a moratorium, is a more targeted tool. Google's pending $50M commitment to Xcel's Capacity*Connect suggests developers will co-fund grid resources when it accelerates their own timeline.
For communities and ratepayers
The measured evidence shows data centers raising costs in concentrated markets. PJM's Dominion zone cleared 64.6% above the RTO-wide capacity price. Harvard's Electricity Law Initiative has documented utilities entering below-cost-of-service contracts with data centers, with the difference recovered from other ratepayers. Cost-reflective rate design (the AEP Ohio model) uses minimum-billing and exit-fee terms to hold data centers to the demand they contract for. Ratepayers can participate by filing comments in utility rate cases and attending state PUC hearings where interconnection rules and tariff structures are decided.
The central question is not whether data center flexibility is technically possible. EPRI proved it is. The question is whether the regulatory and market frameworks that compel flexibility can scale faster than the political backlash that forecloses the opportunity entirely.
If you reference this page in research, regulatory filings, or journalism, the citations below resolve to a stable URL.
APA
Balgeman, C. (2026). Data Centers and the US Grid: Where Load Is Growing and Why It's Constrained. Grid Flexibility. https://gridflexibility.fyi/data-centers
BibTeX
@misc{balgeman2026datacenters,
author = {Balgeman, Corey},
title = {Data Centers and the {US} Grid: Where Load Is Growing and Why It's Constrained},
year = {2026},
howpublished = {Grid Flexibility},
url = {https://gridflexibility.fyi/data-centers},
note = {Last updated 2026-10-01}
}Last updated 2026-10-01. Data sources cited inline throughout the analysis link directly to authoritative origin (FERC, LBNL, Grid Strategies, IEEFA, Utility Dive, EIA, state PUC dockets).
Corey Balgeman · Principal Analyst, Grid Flexibility